HQ

TVM moved into our new HQ in May 2012, this custom fit building will be built to passive haus standard.

 

Ecocem Green Building Award Winner 2013

GreenAwardWinner_2013

 

Official Opening

Marie, Bart, Trisha & Helen Arnold adding their names to the Official Ribbon. [Photo by Una Finn]

 

Aidan McCarthy (Site Foreman MMD), Kevin Galvin (TVM Operations Manager), Helen & Bart Arnold and Cormac Smith (MMD) [Photo by Una Finn]

 

Office Staff celebrating the move!

All those present on the first day at work in the new building.

22nd April – Front of the building finished and tarmac down – starting landscaping soon!

2nd April – Scaffolding removed from Cedar – it’s all starting to come together now!

 

20th March – Cedar Cladding almost finished & stone wall nearly completed

17th February – Cedar Cladding well under way

20th January – Finished render on ‘cottage’

5th December – Tarmac laid behind workshop

7th November – Windows are starting to go in

7th October: External walls going up.

1st September: Foundation for offices and steel work for workshop are up.

 

—–

 

1st July: Sod turned on old cottage site:

Bart & Helen Arnold with members of the TVM team.